Trailside Elementary School

Start Date: 05/01/1999
Completion Date: 06/01/2000
Owner: Anchorage School District
Location: Anchorage, AK
Architects: Porath/Burkhart Architects
Project Manager: Kyle Randich
Project Superintendent: Rick Millar

This project consists of a 58,000 sq ft facility on 15 acres. The new school has 26 classrooms and all core support elements, such as a multi-purpose room with adjacent music room/stage, gymnasium, and IMC. Material procurement and buyout started immediately after award of contract. Earthwork started in May, and by the end of September the building was complete on the exterior, and all sitework substantially complete. The building was complete and turned to the School District for stocking during the Christmas break 1999-2000.