Kincaid Elementary School

Kincaid Elementary School

Start Date: 02/01/1995
Completion Date: 03/01/1996
Owner: Anchorage School District
Location: Anchorage, AK
Architects: nVision
Project Manager: Kyle Randich
Project Superintendent: Greg Pepperd

The project is a 58,000 sq ft facility on 28 acres. The new school has 26 classrooms and all core support elements such as a multi-purpose room with adjacent music room/stage, gymnasium, and IMC. This school bid in January and was two million dollars under the engineers’ estimate. Davis was awarded the contract in February. Material procurement and buyout started immediately. Earthwork started in May and by the end of September the building was complete on the exterior and all sitework substantially complete. The building was complete and turned over to the School District for stocking in March 1996, six months ahead of the contract completion date.