MSB Athletic Fields

MSB Athletic Fields

Start Date: 05/20/2013
Completion Date: 08/01/2013
Owner: Matanuska Susitna Borough
Location: Wasilla, Colony, Palmer, and Houston High Schools
Project Manager: Jerry Bryant
Project Engineer: Cody Troseth
Project Administrator: Darla Hall
Quality Control Manager: Cody Troseth
Site Safety Manager: Kirk Waggoner

Palmer: site drainage improvements, bleachers, site lighting, other improvements to complex buildings.

Colony: site drainage improvements, bleachers, site lighting, running track, other improvements.

Wasilla: new artificial turf, running track, bleachers, security, other improvements.

Houston: new artificial turf, running track, bleachers, security, other improvements.

Work began in May and we were substantially complete in early August 2013.