Providence Southwest Campus Expansion
3840 Piper St., Anchorage, Alaska

Owner: Providence Alaska Medical Center

Architects: RIM Architects

Project Start Date: November, 2004

Project Completion: April, 2006

Sr. Project Manager: Kyle Randich

Project Manager: Nicole Mitchell

Project Engineer: Christine Buckalew

Project Engineer / Quality Control: David Sierks

Site Superintendent: Joe Kowalchuk

Project Administrator: Darla Hall

Project Administrator: Beth Ramsey

 

Working Schedule Dated 1/10/06


 

Day 335 - 4/3/06

Day 336 - 4/4/06

Day 337 - 4/5/06

Day 338 - 4/6/06

Day 339 - 4/7/06

Day 340 - 4/8/06

Day 341 - 4/10/06

Day 342 - 4/11/06

Day 343 - 4/12/06

Day 344 - 4/13/06

Day 345 - 4/14/06

Day 346 - 4/15/06

Day 347 - 4/17/06

Day 348 - 4/18/06

Day 349 - 4/19/06

Day 350 - 4/20/06

Day 351 - 4/21/06

Day 352 - 4/22/06

Day 353 - 4/24/06

Day 354 - 4/25/06

Day 355 - 4/26/06

Day 356 - 4/27/06

Day 357 - 4/28/06

Day 358 - 4/29/06

MEETINGMINUTES

 

4/7/05 - Concrete / Rebar / Forms

click HERE for access to Webcam Link



2/13/06

HUB

2/13/06

HUB

2/13/06

HUB

2/13/06

HUB

2/13/06

HUB

2/13/06

MOB

2/13/06

MOB

2/13/06

MOB

2/13/06

MOB

2/13/06

Skybridge

2/13/06

Skybridge

2/13/06

Parking Garage

2/13/06

Parking Garage

2/13/06

Parking Garage

2/13/06

Parking Garage